Monday, September 11, 2006

Ferma Corporation started adding a layer of dirt on top of the concrete backfill. Later they will be installing a perforated PVC pipe over crushed rock to provide drainage and prevent buildup of water pressure.

Large piles of lumber have been lowered into the basement, and the framing contractors have started working on the interior walls.

This last picture was taken from the top of the Baker tank, looking down into the basement.

This afternoon we drove down to Cornelia's again. Michelle gave us pricing information for some of the faucets, toilets, and sinks that we like.

Friday, September 8, 2006

This morning Ferma Corporation started pouring concrete for the lower portion of the backfill. The recom- mendation in the soils report from Murray Engineers, Inc. calls for concrete up to about 6 feet below site grade. One of the foremen from Granite Rock told me they were estimating it would require 150 yards (over 4,000 cubic feet!) of concrete.

Thursday, September 7, 2006

There was lots of activity at the job site this morning with three groups of sub- contractors working at the same time.

Water- proofing Associates was putting the finishing touches on a layer of Ultraseal.

Jim Giancola Concrete had a worker walking the top of the walls, straightening out all of the hold downs. And there was another worker gettting ready to grind down and smooth out some of the concrete at the base of the walls.

And finally there was another crew (probably the carpenters) snapping chalk lines for the walls.

Tuesday, September 5, 2006

Brad sent me an email today saying they took some core samples from the walls. It tested to 2,910 lbs which is great. I suspect the reason they took samples from the walls is because the day-14 sample that was cast when they poured the walls, did not test very well.

Brad is going to move forward with the waterproofing of the walls and will pour the backfill on Friday.

Correction and update on 9/14/2006:
Brad told me today that the core samples were tested at 2,560 and 2,610 lbs by Granite Rock. The reason why core samples were taken was because the day-14 sample tested to only 1,710 lbs by DCI. Brad said he wants to test the remaining two cast samples at DCI to verify the results obtained by Granite Rock.

Thursday, August 31, 2006

We met with Brad at the job site this afternoon.

One of the four concrete samples, taken by DCI back on August 18, was tested at day 7. Unfortu- nately, the results were below ex- pectations. The sample tested to 1,100 lbs, rather than the expected ~60% or 1,800 lbs at day 7. Brad is going to have them test another sample at day 14 (normally they would have performed the next test at day 28). We're keeping our fingers crossed at this point because if the day 14 results are not good, then we may have a big problem.

In the meantime, the crew from Jim Giancola Concrete has finished removing all of the plywood from the inside of the basement walls. And Waterproofing Associates has started applying the first of two layers of Tremco waterproofing membrane. After that, they'll be attaching Volclay Ultraseal to the walls.

Brad said he'll be pouring the concrete for the backfill next Thursday.

Tuesday, August 29, 2006

I stopped by the job site this morning. It looked like they had filled in the "divots" on the outside of the walls. These were the holes left by the SnapTies after they were broken off.

The crew from Jim Giancola Concrete were busy removing the last few Walers and Jahn "A" brackets from the inside of the wall forms and starting to remove the plywood.

A mini excavator from Ferma Corporation was also there, cleaning up some of the dirt that had collapsed.

Friday, August 25, 2006

Today they started removing the plywood from the outside of the walls and piling up all the used wood at the front of the property. They'll be able to reuse it on a later project.

The basement is really starting to take shape. It looks great!