Brad was also there, meeting with Daniel Mendoza from Mendoza Landscaping. Daniel will be installing the driveway and walkways.
While we were talking an inspector from the city stopped by to look at the trenching for the underground electrical conduit. Brad said he will be backfilling tomorrow and scheduling a mandrel test next week.
Also this morning, we called Michele to order our master bathroom tub, a BainUltra TMU Amma 7242. There's a three-week lead time on that tub, but hopefully it won't hold up the granite work.
This afternoon I brought all of our sinks to the job site and put them in Brad's trailer. Marblus will be there first thing tomorrow morning, to start templating the granite slabs.