Friday, October 13, 2006

The crews from KC Construction and Jim Giancola Concrete were both on site today.

The carpenters were continuing their work on the first floor. Here's one of them putting up the sheathing. Kevin was also there, and he said they will be framing the second floor next week. Then the stackers will start either next Friday or the following Monday. He thinks it will take them about five to seven days to finish the roof. Brad hopes to have the structure water tight by Thanksgiving.

That's Dennis in the second picture, operating a bobcat. He and his crew had already finished filling gravel into the stairwell and they were working on the front porch and back patio forms.