Now that the snow is gone, they are back at it to finish up the year.
Wednesday, December 31, 2008
Friday, December 19, 2008
Snow Delay
We are in a delay because of the weather. There has been snow on the work site for over and week and it looks like we'll get more before Christmas.
Friday, December 12, 2008
Tuesday, December 9, 2008
Monday, December 8, 2008
Friday, December 5, 2008
Wednesday, December 3, 2008
Tuesday, December 2, 2008
Monday, December 1, 2008
Janette's Turn to Pick.
Wednesday, November 26, 2008
Things that will never be seen.
Basement floor is going to be poured on Monday. The rest of this short Thanksgiving week the drainage and basement wall waterproofing is getting done.
Monday, November 17, 2008
Basement
Update: 11-18-08, Plumbers are done. Now I'm not sure what's next. Wait and see.
Tuesday, November 11, 2008
Thursday, November 6, 2008
Basement Walls
Walls are going up. Lots of steelwork and lots of forms. Extra forms since the daylight basement walls are nine feet tall and the forms are eight feet. They worked in the rain, lots of rain.... It rained 1.2 inches from noon till six today. Trying for an inspection on Friday and cement on Monday or Tuesday.
Update 11-08-08:
Inspector has been out and the walls will be poured on Monday.
Monday, November 3, 2008
Cement Footings.
It's permanent now. 5 or 6 trucks of cement later and the footings are in. Tomorrow the forms for the wall will show up. I'm told this will go quick.
Tuesday, October 28, 2008
Monday, October 27, 2008
Wednesday, October 22, 2008
Official Job Site
It's now an official job site, the Honey Bucket is there. Oh, the foundation is ready for forms too.
Saturday, October 18, 2008