Tuesday, February 27, 2007

It was another busy day today -- the job site was bustling with activity again.

The dummy French door leading to the family room was delivered yesterday, and Rob installed it this morning. Troy and Rob are now working on the molding on the first floor.

The installers from Tile Plus started working on the tub surround in Bath #1 and on the laundry room floor.

Dana started installing the kitchen cabinets. Here he is, cutting a small notch in one of the side panels, to accomodate the hardwood floor which will be installed later.

And finally, Carlos' crew was there digging (in the rain) a trench to the main electrical panel.

We also got lots done today!

This morning, we met Ernie at Bedrosians where we selected and purchased all of our remaining slabs: kitchen island (Ubatuba), kitchen counters (Santa Cecilia), master bath (Labrador Antique), and fireplace surround (Mediterranean Beige travertine).

Then later in the afternoon, we met with Claudia and selected all of the interior colors. The main color will be the Oyster (the middle sample in the picture from yesterday's blog entry). Here is the current thinking:
  • craftroom - Skin Light
  • living room - Cappuccino or Westover Hills
  • dining room and power room - Seattle Red
  • family room and kitchen - Skin Light
  • master bedroom - Cappuccino accent wall
  • bedroom #1 - Misty Harbor
  • bedroom #2 - Hillsmere
  • bedroom #3 - French Sonnet
  • bath #2 - Misty Harbor
  • bath #3 - French Sonnet
We also selected the exterior color. Instead of the Wood Moss, we decided to use Chadwick, but darken it up by about 20-25%.