Monday, February 26, 2007

This morning we had a long meeting with Brad, Ernie, and Freddie to go over the tile design. We only had enough time to cover the basement and second floor. We'll have to schedule another meeting to talk about the first floor. That's Ernie, Freddie, and Brad (left to right) talking about the accent tiles in Bath #2.

After the tile meeting, we talked to Troy about the wainscot in the dining room. He had drawn a sample design on the wall for us to look at.

In the early afternoon, Dana showed up to drop off all the kitchen cabinets. They're scattered around the family room and dining room. I think he's going to start installing the cabinets tomorrow.

Later in the afternoon, I returned to the job site and finished painting the three sample interior colors on the pieces of sheetrock I had primed over the weekend. The three colors are (left to right): Chic, Oyster, and Snip of Tannin.

And finally, the last of the three sinks we ordered on the internet (just Wednesday last week) arrived today. The kitchen island sink arrived on Friday, the craftroom sink on Saturday, and the main kitchen sink today, in only five days! We need to puchase one more sink -- for the laundry room, and we ordered it from Cornelia's today. It'll be available for pick-up tomorrow.

We're meeting Ernie at Bedrosians tomorrow morning to choose slabs. And then we have a meeting scheduled with Claudia at the job site to go over paint selections. We can also talk to her about the dining room wainscot.